5MVA 11/0.4kV Distribution Substations At Society Business Park, Lusaka
Client: ZNBS
Funding: NAPSA
Project Cost: US $1.6 Million
Services Offered: Electrical
Year Completed: 2018
Project Description:
The objectives of the project were to construct a substation at the proposed redevelopment of society house and central arcade The Substation was constructed to feed the following areas
A 148 room, 18 Floor Hotel
A two Storey Shopping Mall
A six storey Office tower
Bicon Zambia Limited were tasked with designing, supervision and commissioning of the substation. The Substation was constructed with the following specifications: