Construction OF approximately 340 Km of the Great North Road (T2) from Lukulu Bridge To Chinsali in Northern Province

Client: Government of the Republic of Zambia (GRZ)

Funding: National Road Fund Agency (NRFA)

Project Cost: US $44 Million

Services Offered: Construction Supervision & Design Review.

Project Description:

The main work items undertaken on this road project involved the following:

  • Treatment of surface defects by patching and sealing the existing pavement layers.
  • Shoulder reconstruction of a 150mm chemically stabilised layer.
  • Reconstruction of waterlogged and collapsed road sections.
  • Construction of double seal surfacing.
    Replacement and repair of existing drainage structures.
  • Cleaning and shaping of open drains.
    Providing road furniture.
  • Ancillary works.

After approval of Variation Order No.4, additional and emergency works were implemented on this contract which involved the following:

  • Constructing a rigid pavement on the Mpika Police Check Point.
  • Constructing a rigid pavement on the Mpika Weigh Bridge entrance and exit.
  • Reconstruction and Pothole patching on 200km of Chinsali-Nakonde road.